How do we determine the ideal Work in Progress (WIP) limits for a newly formed Kanban team?


We are transitioning from Scrum to Kanban to handle our continuous flow of maintenance tickets. However, we are struggling with setting our WIP limits. If we set them too low, developers are idle; too high, and nothing gets finished. Is there a mathematical formula or a specific experimental process to find the "sweet spot" for WIP limits without causing team frustration?


   2024-03-14 in Agile and Scrum by Robert Harrison | 13427 Views


All answers to this question.


There is no magic number, but a great starting point is "Number of People + 1." This allows for some flexibility while still forcing a focus on finishing work. The goal of a WIP limit is to make bottlenecks visible. If a column is always at its limit, that is where your process is breaking down. I recommend starting high and gradually lowering the limit until you feel the "tension." When the team starts complaining that they have nothing to do because the "Testing" column is full, you’ve successfully identified that you need more testing capacity, not more development.

   Answered 2024-03-16 by Mary Cunningham


Have you analyzed your "Aging Work" report yet? Sometimes the issue isn't the number of items, but the fact that certain complex tickets are hogging a WIP slot for weeks while smaller tasks are blocked.

   Answered 2024-03-20 by William Peterson

  • Use the "Stop Starting, Start Finishing" mantra. Lower your WIP limits aggressively for one week and watch what happens to your cycle time. It’s a fast way to learn.

       Commented 2024-03-25 by Linda Foster


Use the "Stop Starting, Start Finishing" mantra. Lower your WIP limits aggressively for one week and watch what happens to your cycle time. It’s a fast way to learn.

   Answered 2024-03-25 by Linda Foster

  • I agree, Linda. It sounds counterintuitive to developers to do "less" work at once, but the throughput increases significantly once the multitasking overhead is removed.

       Commented 2024-03-27 by Robert Harrison



Write a Comment

Your email address will not be published. Required fields are marked (*)




Suggested Questions

Introduction to Project Management..
Posted 2026-07-07 by learnersera.
Balancing Link Metrics With Structural Entity Maps..
Posted 2025-05-12 by learnersera.
Balancing Link Metrics With Structural Entity Maps..
Posted 2025-05-12 by learnersera.
Impact of Entity Authority on Organic Competitive..
Posted 2025-01-04 by learnersera.
Backlinks vs Entity Authority for SEO Rankings..
Posted 2025-04-14 by learnersera.
How are modern agile organizations evaluating scrum..
Posted 2025-07-19 by learnersera.
Is a specialized technical degree required to..
Posted 2025-10-05 by learnersera.
How heavily do hiring managers weigh professional..
Posted 2025-09-12 by learnersera.

Disclaimer

  • "PMI®", "PMBOK®", "PMP®", "CAPM®" and "PMI-ACP®" are registered marks of the Project Management Institute, Inc.
  • "CSM", "CST" are Registered Trade Marks of The Scrum Alliance, USA.
  • COBIT® is a trademark of ISACA® registered in the United States and other countries.
  • CBAP® and IIBA® are registered trademarks of International Institute of Business Analysis™.

We Accept

We Accept

Follow Us

 facebook icon
 twitter
linkedin

Instagram
twitter
Youtube

Quick Enquiry Form

WhatsApp Us  /      +1 (713)-287-1187