Does "Responding to Change" mean we should allow stakeholders to change requirements during the middle of a Sprint?

Posted on 2024-05-10 • In Agile and Scrum • By Sarah Jenkins

My team is struggling with the value "Responding to change over following a plan." Our stakeholders think this gives them a license to change the Sprint goals every three days. This is killing our morale and our ability to finish anything. How do we respect the Agile Manifesto while still maintaining a stable environment for the development team to actually produce work?

3 Answers 9,348 Views

All answers to this question 3 Answers

Kimberly Thompson Answered on 2024-05-12
Answered

Responding to change applies to the Product Backlog, not necessarily the active Sprint. The "Plan" in the Manifesto refers to those old 12-month rigid project plans that didn't allow for market shifts. To protect your team, you need to educate stakeholders on the "Cost of Context Switching." If a change is truly urgent, it should be discussed in the next Sprint Planning. If it cannot wait two weeks, then the current Sprint should be cancelled and restarted—a move that usually makes stakeholders realize that their "urgent" change might not be so urgent after all.

David Harris Answered on 2024-05-15
Answered

Are your stakeholders part of the Sprint Review? Often, if they see the progress being made, they are more willing to wait for the next iteration to introduce their new ideas.

Paul Nelson Commented on 2024-05-17
Commented

David, they do attend, but they often use the Review as a place to demand changes for things we just finished. It feels like we are in a constant loop of rework. We are trying to implement a firmer "Lock-in" period for the Sprint, but the business side claims it's not "Agile" enough.

Jessica Carter Answered on 2024-05-20
Answered

Agile is not an excuse for chaos. A plan is still necessary; it just needs to be flexible enough to survive reality. You need a "Definition of Ready" to stop half-baked changes.

Sarah Jenkins Commented on 2024-05-22
Commented

Exactly, Jessica. Following a plan is still 49% of the equation. Without a baseline, you aren't responding to change—you're just reacting to noise.

Write a Comment

Your email address will not be published. Required fields are marked (*)

Join the LearnersEra Community

Ask questions, share knowledge and learn from professionals across technology, project management and certification topics.

Change Country and Nearest City

Select your country and nearest city to see courses available in your region.