How do I handle a Product Owner who constantly changes priorities during an active Sprint?

Posted on 2024-03-14 • In Agile and Scrum • By Sarah Jenkins

I’m currently a Scrum Master for a mid-sized software team, and we are struggling with a Product Owner who keeps introducing new user stories into the Sprint Backlog after the Sprint has already started. This is causing serious scope creep and affecting our velocity. How do you guys manage a stakeholder who doesn’t respect the Sprint Goal without damaging the professional relationship?

3 Answers 14,316 Views

All answers to this question 3 Answers

Rebecca Miller Answered on 2024-03-15
Answered

I’ve faced this exact scenario at my previous firm. The key is to steer the conversation back to the Sprint Goal. When the PO tries to add a new story, I visually demonstrate the impact on the Burndown Chart. It's not about saying "no," but rather "what are we removing to make room for this?" If they insist on the change, you might need to suggest a Sprint Cancellation if the goal is no longer valid, which usually makes the PO reconsider the urgency of the new request.

Mark Thompson Answered on 2024-03-16
Answered

That sounds incredibly frustrating for the developers. Have you tried setting up a formal Backlog Refinement session to ensure the PO has a space to vet these ideas before they hit the Sprint?

Sarah Jenkins Commented on 2024-03-17
Commented

Mark, we do have refinement once a week, but the PO often gets "emergency" requests from the C-suite that they feel they can't ignore. It’s the external pressure that’s the real culprit here. I’m trying to coach the PO on shielding the team, but it’s a slow process.

David Clarkson Answered on 2024-03-18
Answered

The Scrum Guide is clear: only the Developers can change the Sprint Backlog. Remind the PO of the "Definition of Ready" to stop half-baked ideas from sneaking in.

Rebecca Miller Commented on 2024-03-19
Commented

Exactly, David! Enforcing the "Definition of Ready" is a game-changer. It forces the PO to provide clear acceptance criteria before the team even looks at the task.

Write a Comment

Your email address will not be published. Required fields are marked (*)

Join the LearnersEra Community

Ask questions, share knowledge and learn from professionals across technology, project management and certification topics.

Change Country and Nearest City

Select your country and nearest city to see courses available in your region.