How do we interpret a Cumulative Flow Diagram (CFD) to identify process bottlenecks?

Posted on 2024-11-05 • In Agile and Scrum • By Christopher Evans

Our Jira board generates a Cumulative Flow Diagram every month, but it just looks like a bunch of colorful bands moving upward. I’ve heard that the width of the bands can tell you if your process is healthy or failing. Can someone explain in simple terms what a widening band versus a narrowing band means for our team's lead time and throughput?

3 Answers 15,262 Views

All answers to this question 3 Answers

Jennifer Adams Answered on 2024-11-07
Answered

Think of the CFD as a river. The width of a color band represents the amount of Work in Progress in that specific stage. If a band is widening, it means work is entering that stage faster than it is leaving—you’ve found a bottleneck. If the "Testing" band is getting thicker, your testers are overwhelmed. The horizontal distance between the top line (Entered) and bottom line (Done) represents your Lead Time. A healthy CFD should have relatively stable, parallel bands. If the "Done" line is flat, your flow has completely stopped, and you need to investigate blockers immediately.

Daniel Harris Answered on 2024-11-10
Answered

What does it mean if the bands are narrowing? I see this occasionally in our reports and I'm not sure if that is a good sign of efficiency or a bad sign of under-utilization.

David Martinez Commented on 2024-11-13
Commented

Daniel, narrowing bands usually mean your capacity is higher than the demand. While it sounds efficient, it might mean your team is about to run out of work, or you have a "starvation" issue further up the stream (like the Product Owners not refining enough stories). It's a signal to look at your upstream process to ensure the "pipe" stays full enough to keep the team productive.

Elizabeth Young Answered on 2024-11-16
Answered

The slope of the "Done" line is your throughput. A steeper slope means you are delivering more items over time. Watch that line carefully during your monthly reviews.

Christopher Evans Commented on 2024-11-18
Commented

Great point, Elizabeth. We use the CFD slope to forecast our release dates. It's much more accurate than using gut feelings or individual developer estimates.

Write a Comment

Your email address will not be published. Required fields are marked (*)

Join the LearnersEra Community

Ask questions, share knowledge and learn from professionals across technology, project management and certification topics.

Change Country and Nearest City

Select your country and nearest city to see courses available in your region.