How do we manage the Resource Capacity of an Agile team when they are also doing maintenance work?


Our Scrum teams are struggling to hit their sprint goals because "Production Support" tickets keep popping up. How do we account for this unplanned work in our capacity planning without under-committing on our strategic roadmap features?


   2025-11-11 in Agile and Scrum by Brandon Lee | 10359 Views


All answers to this question.


You need to implement a "Capacity Split" during your sprint planning. Most high-performing teams reserve a percentage of their velocity—usually 20% to 30%—specifically for "Maintenance and Bugs." If no bugs appear, the team can pull in items from the top of the backlog. However, if a major issue hits, it’s already budgeted for in your capacity. This prevents the "Whack-a-Mole" effect where unplanned work constantly kills your sprint commitment. It also provides the business with a realistic view of how fast features will actually be delivered, as it acknowledges the reality of running live software.

   Answered 2025-12-05 by Angela Davis


Angela, what if the "Bugs" are so frequent that they take up 80% of the capacity? At that point, aren't we just a support team that occasionally does development?

   Answered 2025-12-10 by Michael Reed

  • Michael, if your support load is that high, you have a "Technical Debt" problem, not a capacity problem. You need to stop the roadmap entirely for one or two sprints to focus on "Root Cause Analysis" and system stability. I’ve seen teams use a "Rotation" where one person is the designated "Firefighter" for the sprint while the others stay 100% focused on features. This protects the deep-work time for the rest of the team while ensuring that support issues still get the immediate attention they need to keep the customers happy.

       Commented 2025-12-15 by Charles Evans


Use a Kanban board for the maintenance work. It allows for a continuous flow of unplanned tasks while your Scrum team continues their time-boxed sprints for the bigger roadmap items.

   Answered 2025-12-20 by Nicole Young

  • This hybrid "Scrumban" approach is very common now. It gives you the structure of Scrum for your projects and the flexibility of Kanban for your day-to-day support issues.

       Commented 2025-12-22 by Brandon Lee



Write a Comment

Your email address will not be published. Required fields are marked (*)




Suggested Questions

Introduction to Project Management..
Posted 2026-07-07 by learnersera.
Balancing Link Metrics With Structural Entity Maps..
Posted 2025-05-12 by learnersera.
Balancing Link Metrics With Structural Entity Maps..
Posted 2025-05-12 by learnersera.
Impact of Entity Authority on Organic Competitive..
Posted 2025-01-04 by learnersera.
Backlinks vs Entity Authority for SEO Rankings..
Posted 2025-04-14 by learnersera.
How are modern agile organizations evaluating scrum..
Posted 2025-07-19 by learnersera.
Is a specialized technical degree required to..
Posted 2025-10-05 by learnersera.
How heavily do hiring managers weigh professional..
Posted 2025-09-12 by learnersera.

Disclaimer

  • "PMI®", "PMBOK®", "PMP®", "CAPM®" and "PMI-ACP®" are registered marks of the Project Management Institute, Inc.
  • "CSM", "CST" are Registered Trade Marks of The Scrum Alliance, USA.
  • COBIT® is a trademark of ISACA® registered in the United States and other countries.
  • CBAP® and IIBA® are registered trademarks of International Institute of Business Analysis™.

We Accept

We Accept

Follow Us

 facebook icon
 twitter
linkedin

Instagram
twitter
Youtube

Quick Enquiry Form

WhatsApp Us  /      +1 (713)-287-1187